Hi All,
I am trying to work on very basic retention policy using RPS but some where I am getting confused with the qualification date calculation.
Scenario is as follows:
1) Create 1phase+final policy
2) Duration is set to 1 day
3) Cutoff period: Monthly, 29th
Phase 1 will be elapsed and moved to the final phase on the basis of the qualification date. So what will be the qualification date here for the document??
Thanks,Tri